- Why there are two kitchen renovation timelines, not one
- How long does a kitchen renovation take in Ireland, week by week
- What decides whether you need planning permission at all
- Why material lead times are the timeline most homeowners never see
- How the two timelines combine into one real completion date
- How to protect the kitchen renovation timeline
- Frequently asked questions
Ask how long a kitchen renovation takes in Ireland and most homeowners hear one number back — six weeks, ten weeks, three months. That number describes only the time trades spend on site. It says nothing about the weeks or months that happen before a single trade arrives, and it is that invisible first timeline, not the one with hammers in it, that most often decides when the kitchen is actually finished.
★★★★★ RATED 4.9/5 BY VERIFIED BUYERS The Kitchen Renovation Blueprint The trades quoting your kitchen have done this a hundred times. Walk in knowing every phase, every cost, every decision — so they price the renovation, not your inexperience. See what's inside → Instant download · 30-day money-back guaranteeA kitchen renovation timeline in Ireland is really two timelines running side by side: the planning and procurement timeline, which covers permission, design, and ordering; and the on-site build timeline, which covers demolition through to snagging. Homeowners plan around the second one and get blindsided by the first.
The kitchen build takes six to ten weeks. The kitchen renovation takes as long as its slowest timeline — and that is rarely the build.
This guide sets out both timelines in full — the realistic week-by-week build schedule, and the planning, design, and lead-time clock that runs alongside it and usually finishes later. The full trade sequence behind the build weeks below is set out in the kitchen renovation order of trades in Ireland, and what each stage costs is in the kitchen renovation cost guide for Ireland.
Why there are two kitchen renovation timelines, not one
Because a kitchen renovation has two separate clocks, and only one of them is visible once the skip arrives. The build timeline is what a homeowner watches — strip-out, first fix, plasterboard, units, worktop, snagging. It is countable in weeks, it has trades in the house, and it produces visible progress every day.
The planning and procurement timeline is invisible by comparison. It covers whether planning permission is required, the design and specification process, the quotes and contract, and the lead time on units, worktops, and appliances once ordered. None of that timeline puts a trade in the house, which is exactly why homeowners overlook it — there is nothing to watch, so there is nothing to remind them it is running.
The two timelines do not run one after the other. They overlap, but only if the homeowner starts the second one — ordering units, confirming a Commencement Notice, booking trades — well before the build is meant to start. A homeowner who waits until the design is finalised to order units has, in effect, added the entire procurement timeline onto the front of the build, turning a ten-week project into a four-month one.
How long does a kitchen renovation take in Ireland, week by week
For a kitchen renovation that does not require planning permission — the majority of Irish kitchen renovations — the on-site build timeline runs roughly six to ten weeks from strip-out to snagging. Where a wall comes down, services are relocated, or the kitchen connects into an extension, the build timeline moves to the upper end of that range or beyond.
- Week 1 — strip-out and first fix begins. The old kitchen comes out, and the plumber and electrician start the buried first-fix work — supply, waste, gas line if required, and the electrical circuits — while the walls and floor are still open.
- Weeks 1–2 — building work, if any. Where a wall is moved or an opening created, this structural work happens before the first fix is completed, and it is the stage most likely to uncover something the original quote did not price — old wiring, a damp subfloor, a wall that is not where the plans said it was.
- Weeks 2–3 — plasterboard, skim, and paint. With the first fix signed off, the walls are boarded, skimmed, and painted while the room is still empty and easy to access.
- Week 3 — flooring. The floor covering goes in and runs under where the units will sit, so there is a continuous surface rather than a unit-height lip.
- Weeks 4–5 — units install. The units are delivered, installed, and levelled — assuming they were ordered in week one, this is the stage where a homeowner who waited to order discovers the gap between when units are needed and when they arrive.
- Weeks 5–7 — worktop template, fabrication, and install. The worktop can only be templated once the units are in and level, and stone typically takes one to two weeks to be cut and returned — a gap where the kitchen has units but no working sink.
- Weeks 7–8 — splashback, second fix, and appliances. The splashback is fitted, and the plumber and electrician return to connect the sink, taps, hob, oven, and appliances now that everything they connect to exists.
- Weeks 8–10 — snagging and final sign-off. The finished kitchen is checked against the brief — unit alignment, worktop joints, appliance function, no leaks — before the snagging list is cleared and final payment is released.
Get your build timeline priced first
The free Renovation Cost Calculator gives you a trade-by-trade estimate in under 5 minutes — before your first trade conversation. It shows what each week of the build actually costs, so the timeline and the budget are built from the same numbers.
What decides whether you need planning permission at all
Most kitchen renovations in Ireland do not need planning permission, and that single fact is the biggest variable in how long the overall renovation takes. Internal kitchen renovations are generally classed as exempted development, provided the use of the building and its external appearance are unchanged — replacing units, worktops, flooring, and appliances within the existing footprint does not trigger an application. Where the confirmed position sits is set out by Citizens Information.
The exemption has a limit. If the kitchen is being extended — a rear extension to create a larger space, for instance — planning permission is only required once the works exceed the exempted-development thresholds, broadly an extension up to 45 square metres subject to conditions on height and position. Cross that line and the timeline changes completely: a local authority has up to eight weeks to decide a planning application, and that clock only starts once the application is validated, before any appeal or further-information request extends it again.
Even a kitchen that stays inside the existing walls and needs no planning permission is not necessarily free of process. Where the work is a material alteration to the structure, a Commencement Notice must be lodged with the local authority's Building Control between 14 and 28 days before work begins — a distinct, mandatory notification that is not planning permission and is easy to miss because nothing about a kitchen renovation feels like it should require a government filing.
A kitchen that stays inside the existing walls and does not relocate services can realistically be finished in six to ten weeks of on-site work, with a Commencement Notice as the only mandatory filing.
A kitchen that extends the footprint enters a different timeline entirely — a planning application that can take eight weeks minimum to decide, before the build clock even starts. Confirming which fork applies is the single highest-leverage question to answer before setting any completion date.
Why material lead times are the timeline most homeowners never see
Kitchen units in Ireland typically carry a lead time of six to ten weeks from order to delivery — meaning the units have to be ordered before the design is finished being refined, not after. A homeowner who finalises every cabinet detail before ordering has, without realising it, added the entire lead time onto the start of the build rather than running it in parallel.
Stone and quartz worktops compound the problem from the other direction. The worktop cannot be templated until the units are installed and level — itself weeks four or five of the build — and fabrication and return then take a further one to two weeks. That dependency is why a timeline that looks like ten weeks on paper regularly runs to twelve or more when ordering does not overlap with the planning and design phase.
The lesson is not that Irish kitchen renovations are slow. It is that the procurement and build timelines have to run together, and the only way to do that is to order the long-lead items — units first, then worktop material — as soon as the design is locked, not once every other decision is also finalised.
How the two timelines combine into one real completion date
The real completion date for a kitchen renovation in Ireland is the later of two dates: when the build timeline finishes, and when the planning and procurement timeline releases the site to start building at all. Most homeowners calculate only the first date and are surprised when the second one turns out to be the one that actually governs.
For a straightforward kitchen needing no planning permission, the two timelines can run almost entirely in parallel — confirm the Commencement Notice window, finalise the design, and order the units, all while quotes are still being compared, so that by the time strip-out begins the units are already in transit rather than just ordered. For a kitchen that requires planning permission, the procurement timeline has to wait behind the planning decision, so the honest total runs from the date the application is lodged, not the date a trade first picks up a tool.
This is the same twin-timeline discipline that runs through every renovation regardless of room, set out in full in the 12 phases of a renovation in Ireland. A kitchen simply makes the gap between the two timelines more visible, because the build weeks are short enough that a slow planning or procurement timeline dwarfs them rather than hiding inside them.
How to protect the kitchen renovation timeline
Protecting the timeline is a sequencing discipline, not a scheduling trick, and it rests on running the invisible timeline at the same time as the visible one rather than waiting for one to finish before starting the other.
- Confirm the planning position before setting any date. Establish whether the kitchen stays within exempted development or crosses into planning-permission territory before promising anyone — including yourself — a completion month, because the two forks produce completely different timelines.
- Lodge the Commencement Notice as soon as the design is fixed. The 14-to-28-day window before work begins should overlap with the final weeks of procurement, not add extra time after everything else is ready.
- Order the units the day the design is locked, not the day it is perfected. A six-to-ten-week lead time run in parallel with quotes and contract review costs nothing; the same lead time started after strip-out costs the entire build schedule.
- Book every trade before the first one starts, not as each stage finishes. A kitchen sequenced trade-by-trade rather than pre-booked end-to-end loses days between each stage waiting for the next trade's availability.
- Treat the worktop template gap as planned, not a delay. The one-to-two-week wait between the units going in and the worktop returning is normal; planning a temporary kitchen setup for that window keeps it from feeling like the project has stalled.
None of these five steps shortens the build itself. They remove the dead time between the two timelines — the days and weeks a kitchen renovation loses not because a trade worked slowly, but because the invisible timeline was never started early enough to finish alongside the visible one.
The Kitchen Renovation Blueprint runs both timelines side by side from the first decision — the planning check, the design lock, the ordering schedule, and the trade sequence — so a prepared homeowner sets one real completion date instead of discovering two.
See The Kitchen Renovation Blueprint
Every phase of an Irish kitchen renovation — the planning check, the ordering schedule, and the build sequence — run together instead of one after the other.
If the cost baseline is the right first step, use the free Renovation Cost Calculator — a trade-by-trade estimate for the specific kitchen, in under 5 minutes, before any trade has quoted.
Frequently asked questions
How long does a kitchen renovation take in Ireland?
The on-site build timeline for a kitchen renovation that does not require planning permission typically runs six to ten weeks, from strip-out to snagging. Where a wall is moved, services are relocated, or the kitchen connects into an extension, the build runs at the upper end of that range or beyond. This figure covers only the on-site build — it does not include the planning, design, and procurement timeline that has to run before or alongside it.
What are the two timelines in a kitchen renovation?
The build timeline covers the weeks trades spend on site — strip-out, first fix, plasterboard, units, worktop, and snagging. The planning and procurement timeline covers whether planning permission is required, the design and specification process, quotes and contract, and the lead time on units and worktops once ordered. Homeowners plan around the build timeline and are frequently surprised by the procurement timeline, because it produces no visible progress to track.
Do I need planning permission for a kitchen renovation in Ireland?
Usually no. Internal kitchen renovations are generally classed as exempted development provided the use and external appearance of the building are unchanged. Planning permission is only required if the kitchen is being extended beyond the exempted-development thresholds. Where planning permission is required, the local authority has up to eight weeks to decide, and that clock only starts once the application is validated.
How long is the lead time on kitchen units and worktops?
Kitchen units in Ireland typically carry a lead time of six to ten weeks from order to delivery, so they need to be ordered as soon as the design is locked rather than after every finishing detail is decided. Stone and quartz worktops cannot be templated until the units are installed, and fabrication and return then take a further one to two weeks — a normal gap in the schedule, not a delay.
What is a Commencement Notice and does a kitchen renovation need one?
A Commencement Notice is a mandatory filing with the local authority's Building Control, required where a renovation involves a material alteration to the structure, and it must be lodged between 14 and 28 days before work begins. It is separate from planning permission and applies even to kitchens that do not require a planning application, which is why it is often missed until it stalls the start date.
Why do kitchen renovations often take longer than the quoted build time?
Because the quoted build time usually describes only the on-site weeks, not the planning and procurement timeline that has to happen first or alongside it. A homeowner who waits until the design is finalised to order units, confirm the Commencement Notice, or book trades has effectively added the entire procurement timeline onto the front of the build, turning a ten-week project into a four-month one without any single trade working slowly.