- Phase 1: Project Brief and Space Planning
- Phase 2: Budget Setting and Cost Validation
- Phase 3: Design Finalisation and Specification
- Phase 4: Trade Shortlisting and Quote Process
- Phase 5: Quote Evaluation and Comparison
- Phase 6: Contract Review and Pre-Signing Checklist
- Phase 7: Procurement and Long-Lead Scheduling
- Phase 8: Demolition and Rough-In Works
- Phase 9: Waterproofing and Hold-Point Sign-Offs
- Phase 10: Fit-Out and Finishes
- Phase 11: Defects Inspection and Rectification
- Phase 12: Final Payment and Sign-Off
- The Kitchen Renovation Electrical Checklist
- The Complete Kitchen Renovation Checklist — Summary
- Frequently Asked Questions
Most Australian renovation budgets don't blow out because of the renovation. They blow out because of the conversations.
★★★★★ RATED 4.9/5 BY VERIFIED BUYERS The Kitchen Renovation Blueprint The trades quoting your kitchen have done this a hundred times. Walk in knowing every phase, every cost, every decision — so they price the renovation, not your inexperience. See what's inside → Instant download · 30-day money-back guaranteeThe number one reason renovations exceed their budget is not materials. It is not bad luck. It is not even bad design. It is the series of conversations between the homeowner and the trades — about quotes, variations, milestone payments, and defects — where one party has done this hundreds of times and the other is doing it for the first time. The information sits on one side of the table. The bill sits on the other. A kitchen renovation checklist is what moves the information back to your side.
Every kitchen renovation in Australia follows the same sequence of decisions — the twelve phases every renovation runs through, applied to the kitchen. The homeowner who has a checklist for each of those decisions gets a fundamentally different outcome than the one who makes them on the run, on site, under pressure. This is the complete kitchen renovation checklist — every phase, every decision point, every question you should be ready to answer before your trades answer it for you. Each of those phases is built out as a working document — scope templates, quote comparisons, and hold-point sign-offs — in the Kitchen Renovation Blueprint planning system.
Every renovation follows the same sequence of decisions.
The checklist is the difference between an outcome you control and one you experience.
Phase 1: Project Brief and Space Planning — Define the Scope Before You Talk to Anyone
The most expensive mistake in renovation planning is changing the scope after the contract is signed. Every scope change made mid-build costs more than the same decision made before anyone picked up a tool. So before you contact a single trade, you need to know exactly what you are renovating. Not roughly. Exactly.
A full strip-out and rebuild is a fundamentally different project from a cosmetic update with new doors, new benchtops and a fresh splashback. In the Australian market, those two projects can be twenty thousand dollars apart for the same kitchen. Knowing which one you're doing — and knowing it before any trade walks through your door — is the single biggest cost-control decision in the project.
Lock these decisions before quoting:
- Layout — same footprint or moving walls? If walls are moving, you need structural assessment before anything else. The cost difference between like-for-like and a layout change is significant — moving plumbing in particular is the single largest cost lever in a kitchen renovation.
- Every fixture and fitting being replaced. List the lot: cabinetry, benchtop, splashback, sink, tapware, cooktop, oven, rangehood, dishwasher, lighting, flooring. If it is not on the list, it will not be in the quote. If it is not in the quote, it will be a variation.
- Plumbing relocation. Moving a sink or dishwasher position changes the scope, the cost, and the trades required. The decision to keep or move the sink is worth thousands.
- Electrical changes. Additional power points, under-cabinet lighting, rangehood ducting — all of this requires rough-in work before walls are closed. Add it now or pay double for it later.
- Budget range — floor and ceiling. Not a single number. Know the most you'll spend and the least you can deliver the project for. The Australian market in 2026 sits roughly between $15,000 for a basic refresh and $100,000-plus for a premium custom build. Most mid-range kitchens land between $30,000 and $60,000.
Not sure what your kitchen renovation should cost? The free Renovation Cost Calculator gives you a trade-by-trade estimate in under 5 minutes — before your first trade conversation.
This is also where most homeowners discover what the difference between a prepared and unprepared homeowner actually means in dollar terms. The unprepared homeowner enters Phase 2 with a wishlist. The prepared one enters with a scope.
Phase 2: Budget Setting and Cost Validation
A scope without a number attached is a wish. A number without a scope attached is a guess. Phase 2 turns the decisions from Phase 1 into a figure you can actually defend when the quotes come back higher than you hoped.
Set a range, never a single number. You need a floor — the least you can deliver this project for without regretting it — and a ceiling, the most you will spend before the project stops making sense. A single figure gives you nothing to negotiate against, because the moment a quote exceeds it you have no way of knowing whether to push back or walk away.
Anchor both figures to the market rather than to what you hope to spend. The range from Phase 1 — $15,000 at the cosmetic end, $100,000-plus at the premium end, most mid-range kitchens between $30,000 and $60,000 — is the reality your floor and ceiling have to sit inside. Where yours falls is decided almost entirely by the Phase 1 answers, and above all by whether plumbing moves. The HIA Kitchens and Bathrooms Report tracks where sector activity and pricing are heading each quarter — useful context when a quote lands well outside the range you expected.
Validate the number trade by trade. A single lump figure hides which trade is the one blowing your budget. Break it down: demolition and disposal, plumbing, electrical, plastering, tiling, cabinetry, benchtop, appliances, painting, final clean. If you cannot put a rough figure against each line, you are not ready to receive quotes — you are ready to be quoted at.
- Floor figure set — the least you can deliver the project for
- Ceiling figure set — the most you will spend
- Contingency of 15 to 20 percent held separately, not inside the build budget
- Cost broken down trade by trade, not carried as one lump figure
- Temporary living costs budgeted — most Australian families spend an extra $2,000 to $5,000 on takeaway and groceries while the kitchen is out
- Budget tested against the actual scope from Phase 1, not against a number you hoped for
The contingency is the line most homeowners get wrong. Held inside the build budget it gets spent on an upgrade in week two and is gone by the time the real surprise arrives. Held separately, it does the job it exists for.
Phase 3: Design Finalisation and Specification
Every selection has to be locked before anyone is asked to price the work. Not narrowed down. Not shortlisted. Locked, in writing, with model numbers.
This is the phase homeowners most often postpone, because it feels like the fun part and there is always more to look at. Postponing it is expensive. A cabinetmaker cannot start without appliance specifications — the joinery is built around the oven, the cooktop cut-out and the dishwasher cavity. A benchtop cannot be templated against a layout that might still change. Every selection left open becomes a variation later, priced at a moment when you have no leverage left.
- Cabinetry colour and finish
- Benchtop material
- Benchtop edge profile
- Tile size, colour and pattern
- Splashback material
- Tapware and sink
- Handles
- Appliance brands and model numbers — the spec sheets drive the joinery
- Lighting specification, including under-cabinet
- Flooring, and whether it runs under the cabinetry or up to it
Nothing is left as "to be confirmed" once the build begins. Record every selection in one document and give the trade a copy. When a question arises in week four — and it will — the answer is already written down, and it is written down in your words rather than decided on site without you.
Phase 4: Trade Shortlisting and Quote Process
Finding the right trades is a different job from finding available ones. The trade who can start next week is not automatically the trade you want, and in a market where good kitchen fitters are booked months ahead, immediate availability is worth asking questions about.
Approach three, not one, and not seven. One gives you no comparison. Seven gives you a spreadsheet you will never finish and a reputation among local trades for shopping rather than buying. Three genuinely comparable quotes is the number that lets you see the shape of the market without exhausting yourself or the people quoting.
- Licence or registration number verified against your state's regulator — not just quoted on the invoice
- Public liability insurance confirmed as current
- Home warranty insurance available for the contract value where your state requires it
- Recent kitchens seen — photographs at minimum, a completed job in person if you can
- References from the last twelve months, not the last decade
- The written scope document from Phase 1 issued to every trade, identically
- The same deadline given to all three, so the quotes arrive together and can be read together
Issue the same scope document to every trade, without editing it between conversations. The moment one trade is working from a slightly different brief, the quotes stop being comparable and Phase 5 becomes guesswork.
Phase 5: Quote Evaluation and Comparison — Get Quotes That Are Actually Comparable
Three quotes that look different are not three comparable options. They are three different interpretations of a project that was never properly specified.
The trade who includes demolition and disposal in their quote looks expensive next to the trade who excluded it. The trade who supplies and installs the cabinetry looks expensive next to the trade who only installs. Neither quote is wrong. They are answering different questions — because no written scope document existed to make them answer the same one. This is the moment most kitchen renovation budgets are quietly set against the homeowner.
Before requesting any quote, write a scope document. It does not need to be long. It needs to be specific. Every line item: demolition. Disposal. Plumbing rough-in. Electrical rough-in. Waterproofing. Plastering. Tiling. Cabinetry. Benchtop fabrication and installation. Appliance installation. Painting. Final clean. If it is not written down, it will be interpreted differently by every trade who quotes it. Send the identical document to every trade. Specify what you are supplying and what the trade is supplying.
When the quotes come back, run every one against this list:
- Does the quote address every line item in your scope document?
- Are provisional sums and prime cost items identified with specific allowance amounts — not left open?
- Is a timeline included with start and estimated completion dates?
- Are payment terms tied to completed stages — not to calendar dates or percentages of time elapsed?
- Is the trade's licence or registration number included?
- Does the quote explicitly state what is excluded?
- Is there a clause about how variations will be handled — including that no variation work begins until the variation is signed?
Every item you cannot tick is a gap. Every gap is a place where money moves in the trade's favour later, because nothing was agreed in writing now. This is the foundation behind everything in how to read a renovation quote — a quote is not a price, it is a negotiating position, and the document you send it against is what disciplines that negotiation.
Phase 6: Contract Review and Pre-Signing Checklist — Review the Contract Before You Sign It
The contract governs every dispute, every variation, and every payment for the entire renovation. Most homeowners read the total price and the timeline and sign. The prepared homeowner reads everything else.
In Australia, residential building contracts are state-regulated, and each state's consumer building authority publishes guidance on what the contract must contain. Read this guidance before you sign — see NSW Fair Trading, Consumer Affairs Victoria, QBCC Queensland, Building and Energy WA, Consumer and Business Services SA, or CBOS Tasmania depending on your state.
Your pre-contract checklist:
- Full scope of works matches your written scope document, line by line, not summarised
- Total contract price matches the accepted quote exactly
- Payment schedule tied to completed stages of work — never to calendar dates or percentages of time elapsed
- Variation clause requires every change to be agreed in writing, with cost confirmed and signed by both parties, before work on the variation begins
- Defects liability period stated explicitly — your window to raise issues after practical completion
- Insurance details confirmed: the trade carries the public liability and home warranty insurance required in your state
- Dispute resolution mechanism included
- Provisional sums and prime cost items listed with specific allowance amounts
- Deposit terms comply with state regulations
If any of these items are missing from the contract, do not sign until they are added. A contract that protects both parties is not adversarial. It is professional. The trade who resists putting things in writing is telling you how they manage projects.
Phase 7: Procurement and Long-Lead Scheduling — Prepare the Site Before Demolition Begins
The two weeks before demolition are the most underrated phase of any kitchen renovation. What you do here determines whether the next six to twelve weeks are controlled or chaotic.
Pre-build checklist:
- Temporary kitchen set up. Kettle, microwave, portable cooktop, washing-up station. You will use this for weeks. Make it functional, not an afterthought. Plan to spend an extra $2,000 to $5,000 on takeaway and groceries during the renovation period — most Australian families do, and it should be in the budget.
- All personal items removed from the kitchen and adjacent rooms.
- Dust barriers installed between the renovation zone and the rest of the home.
- Trade access arrangements confirmed — keys, codes, parking, working hours.
- Neighbours notified of dates and expected noise.
- All materials and fixtures ordered with confirmed delivery dates that align to the installation schedule. Custom cabinetry has the longest lead time in any kitchen renovation — typically 4 to 8 weeks for semi-custom and 8 to 14 weeks for fully custom. Order it the day the design is locked, not the day demolition starts.
- Every selection finalised in writing. Cabinetry colour. Benchtop material and edge profile. Tile size, colour and pattern. Splashback material. Tapware and sink. Handles. Nothing left as "to be confirmed" once the build begins.
The rule: no decision should be made on site during the build that could have been made before it started. Every decision made under time pressure on a demolition site costs more than the same decision made at a desk — usually because the trade has already started the work and a change becomes a variation.
If you're working full time around this, the pre-build phase is where the entire renovation is won or lost. The detail on how to make this work around a job is in managing the renovation while working full time.
Phase 8: Demolition and Rough-In Works — Manage the Build
Demolition is fast. The rough-in phase that follows — plumbing, electrical, and any structural work behind the walls — is where the real infrastructure of your kitchen is built, and where most homeowners lose visibility of what is actually happening.
During demolition:
- If the home was built before 1990, confirm that an asbestos assessment has been completed before any work begins. This is a legal requirement in most parts of Australia and a safety one everywhere.
- Demolition waste is removed and disposed of properly — skip bin and tip fees ($300 to $600) sometimes excluded from quotes.
- Any structural elements identified as load-bearing are confirmed by an engineer before removal.
During rough-in:
- Plumbing rough-in matches the approved layout. Verify pipe positions for the sink, dishwasher, and any other water connections before they are covered. In Australia, plumbing must be carried out by a licensed plumber — DIY plumbing is illegal in every state and territory and voids your home insurance.
- Electrical rough-in includes every power point, lighting circuit, switch location, and rangehood ducting run. Check it against your plan. Once the walls are closed, changes are expensive — same legal rule applies; only licensed electricians may carry out the work.
- Photograph every rough-in before it is covered. These photos are your only record of what is behind the walls. Take them yourself. Date them. Save them in a place you will still have access to in ten years.
This is also the phase where the homeowner's role shifts from buyer to manager — and where the difference between a renovation that goes smoothly and one that drifts becomes most visible. The mechanics of how to do this without hiring a project manager are covered in project-managing the renovation without hiring a project manager.
Phase 9: Waterproofing and Hold-Point Sign-Offs — The Inspection You Cannot Skip
If your kitchen renovation involves plumbing relocation or any wet area modification, waterproofing must be inspected and certified before any tiling begins. This is not optional. It is not a step that can be compressed for time. A waterproofing failure that surfaces eighteen months later means every tile is removed. The entire surface is stripped back to the membrane. The cost is significant, the disruption is severe, and it is entirely preventable with one inspection at the right moment.
If your trade suggests tiling can start before the waterproofing inspection is signed off, that is a red flag — not a time-saving suggestion. Waterproofing is the only stage where a single hour of cutting corners produces a defect that takes weeks and tens of thousands of dollars to fix. Hold the line on this one.
Waterproofing checklist:
- Membrane applied by a qualified, licensed waterproofer
- Inspection completed and certificate of compliance issued before any tiling begins
- Compliance certificate added to your project records and stored permanently
- Photographs of the membrane taken before it is covered
Australian Standard AS 3740 governs waterproofing of wet areas in residential buildings, and the certificate is the document that proves compliance. The day the certificate is in your hand, tiling can begin. Not before.
Phase 10: Fit-Out and Finishes — The Sequence That Matters
This is the phase where your kitchen becomes visible. Cabinetry, benchtops, splashback, appliances, and finishing trades all converge — and the order in which they arrive matters more than most homeowners realise.
The correct fit-out sequence for a standard kitchen renovation is the build logic every experienced trade follows. Getting it wrong creates idle trade days, rework, and cost. A benchtop templated before cabinets are installed will not fit. A splashback installed before the benchtop creates a gap that cannot be properly sealed. The sequence is not a suggestion. It is the order things must happen.
The 10-step kitchen fit-out sequence:
Cabinetry installation
First because every other measurement is taken off it.
Benchtop template
Measured after cabinets are installed, never before.
Benchtop fabrication
Typically 5 to 10 business days from template.
Benchtop installation
Fitted to the templated cabinets.
Plumbing connections
Sink, dishwasher, and any gas.
Splashback installation
After the benchtop is in place, never before.
Electrical fit-off
Power points, rangehood connection, under-cabinet lighting.
Painting
After every fixed element is installed, so cut lines are clean.
Appliance installation
Into a kitchen that's now finished around them.
Final clean
Full kitchen and adjacent rooms before handover.
A note on benchtops in 2026: engineered stone with crystalline silica content above 1% has been banned in Australia since 1 July 2024 under Safe Work Australia regulations. If your kitchen renovation includes engineered stone, the product must be either low-silica (under 1%) or a silica-free alternative such as porcelain slab or sintered stone. Most stonemasons have already moved over. Confirm what your benchtop is before signing the order — the cost is similar, and the compliance is on you to verify.
The Kitchen Renovation Blueprint covers every phase in full — including the working tools you use during the actual renovation: budget tracker, variation log, milestone payment tracker, defects list, and a site reference card you take to every visit.
Phase 11: Defects Inspection and Rectification — Protect Your Position
The renovation looks finished. The trades are ready to leave. This is the moment where the prepared homeowner and the unprepared homeowner diverge for the last time.
Before releasing final payment, inspect and document:
- Every cabinet door opens and closes without catching or resistance
- All drawers slide smoothly and sit flush when closed
- Benchtop joins are level with no visible gaps or lippage
- Tile grout is consistent with no cracks, voids, or discolouration
- Every power point and switch is operational
- Plumbing has no leaks — run every tap and the dishwasher under pressure for at least ten minutes
- Rangehood ducting is connected and extracting correctly to the outside
- Paint finish is even with no patches, drips, or missed areas
- All appliances are installed, levelled, and functioning
- All compliance certificates have been issued and collected — including the waterproofing certificate from Phase 9
Document every defect in writing. Issue the list to the trade before the final payment is even discussed. In most Australian states, you are entitled to withhold a reasonable amount until the work is completed to the standard specified in the contract — the precise mechanism is set out in your contract's defects liability clause and your state's residential building law.
Once final payment is released, your leverage to get defects fixed drops dramatically. This is not about distrust. It is about maintaining the professional framework that has protected both parties from the first conversation to the last. The trade who has built a career on fixing what they install will fix it. The trade who has not, will not. The contract you wrote in Phase 6 is the document that makes the difference.
Phase 12: Final Payment and Sign-Off
The defects are documented. The rectification is either done or scheduled. Phase 12 is closing the project properly — legally and financially — rather than letting it trail off.
Final payment is not a formality. It is the moment the defects liability period starts running, and the moment any amount you withheld under the Phase 6 contract terms is released — which is why both need a written date against them on the same day. A defects liability period nobody recorded a start date for is a warranty you cannot enforce when something fails in month ten.
- Every documented defect either rectified or formally agreed in writing with a date
- All compliance certificates collected and filed — including the waterproofing certificate from Phase 9 and the electrical certificate of compliance
- Warranty documentation received for appliances, benchtop and cabinetry
- Defects liability period start date confirmed in writing
- Any retention or withheld amount released only against completed rectification
- Final invoice matches the contract sum plus signed variations — nothing else
- Photographs of the completed kitchen taken and stored with the project file
Keep the whole project file. Certificates, the signed contract, every variation, the defects list and the rough-in photographs from Phase 8. It is the documentation that answers questions about the kitchen years later — when you sell, when you insure, or when something fails inside its warranty period.
The Kitchen Renovation Electrical Checklist
Electrical is the trade where the homeowner's decisions are made weeks before anything is visible and cannot be changed cheaply afterwards. Everything below is settled at the Phase 8 rough-in, before the plasterboard closes.
Who is allowed to do the work. Building Commission NSW states you must hold an electrical licence before undertaking any electrical wiring work in NSW, regardless of the cost or type of work. Victoria requires every electrical worker to be licensed by Energy Safe, and an electrician must work for a Registered Electrical Contractor to perform work for a customer. Treat unlicensed electrical work as unavailable to you wherever your kitchen is.
Circuits and RCD protection. The 2018 edition of the Australian and New Zealand Wiring Rules, applied on a mandatory basis from 1 January 2019, requires residual current devices on all domestic and residential final sub-circuits — not only power points, but lighting and fixed appliance circuits as well. A kitchen that adds circuits usually triggers switchboard work, and an older board without RCD protection is a cost most kitchen quotes quietly exclude. Ask about it in Phase 5, when you can still price it, rather than at rough-in when you cannot.
What to confirm at rough-in, in writing.
- Dedicated circuits confirmed for the oven, the cooktop and every other fixed appliance the manufacturer specifies — read the appliance manuals before rough-in, not after delivery
- Switchboard capacity and RCD protection assessed, with any upgrade priced inside the contract rather than discovered as a variation
- Power point count and positions marked on the wall against the final cabinetry drawing, including the island, appliance garages and charging points
- Supply points for the rangehood, dishwasher, microwave and integrated appliances located for the exact appliances specified in Phase 3, not generic positions
- Under-cabinet and in-cabinet lighting agreed, with driver and transformer locations accessible for replacement
- Isolation switches for fixed appliances positioned so they can be reached without moving the appliance
- Rough-in photographed before the plasterboard closes, with the photographs filed against the project record
The certificate you must receive. Electrical compliance is certified state by state. In New South Wales the electrician must submit a Certificate of Compliance for Electrical Work to Building Commission NSW no later than seven days after the electrical test is completed, and from 1 July 2026 every certificate must be lodged through the BCNSW eCert portal — handwritten and PDF forms are no longer accepted. Ask your electrician to enter your email address as they complete it, so your copy is sent automatically when the certificate is lodged. In Victoria the equivalent is a Certificate of Electrical Safety issued under the Electricity Safety Act 1998, and where the work is classed as prescribed it must also be inspected by an independent Licensed Electrical Inspector that your Registered Electrical Contractor arranges. Confirm which category your job falls into before the work starts.
File the electrical certificate alongside the waterproofing certificate from Phase 9. Phase 12 does not close without both.
The Complete Kitchen Renovation Checklist — Summary
Twelve phases. Every kitchen renovation in Australia runs through all of them, in this order — the same twelve phases The 12-Phase System is built around. The homeowner who runs this checklist gets a fundamentally different outcome than the one who doesn't.
- Before you start: Scope defined. Budget range set. No decisions left open.
- Quotes: Written scope document sent to every trade. Three genuinely comparable quotes received. Each evaluated against the same criteria.
- Contract: Every clause reviewed. Payment schedule tied to completed stages. Variation process agreed in writing. Defects period stated.
- Pre-build: Temporary kitchen ready. Cabinetry ordered. Every selection finalised in writing.
- Demolition and rough-in: Asbestos checked if pre-1990. Every rough-in photographed before walls close.
- Waterproofing: Inspected and certified before tiling. No exceptions.
- Fit-out: Correct sequence followed. Cabinetry → template → fab → install → splashback → electrical → paint → appliances.
- Defects and payment: Every defect documented in writing. Final payment withheld until rectified.
A typical mid-range kitchen renovation in Australia takes six to ten weeks total — three to five weeks of which is active disruption with no functioning kitchen. Published estimates of how much of that cost comes back at resale vary widely, and depend far more on your local market than on your finishes — treat any single percentage you are quoted with suspicion. The disruption is temporary. The decisions documented above last twenty years.
What This Checklist Does Not Cover
This kitchen renovation checklist gives you the decision points. What it does not give you is the working infrastructure to manage every one of them across an eight to twelve week renovation — the budget tracker that shows you where you are against your original numbers in real time, the variation log that documents every scope change with its cost and approval, the milestone payment tracker that ties every dollar released to a verified stage, and the site reference card that puts every checkpoint in your hand when you walk on site.
That is what the planning systems at Property Blueprint Co. are built to do.
→ See what is inside the Kitchen Renovation Blueprint
Every phase. Every decision. Every working tool you use during the renovation. Built for the Australian homeowner who has decided to manage their own kitchen renovation and wants the system that makes it possible.
View the Kitchen Renovation Blueprint →
Or see all Property Blueprint Co. planning systems if you're renovating more than the kitchen.
The free Renovation Cost Calculator gives you a trade-by-trade estimate in under 5 minutes — before your first trade conversation. Run your number now.
Frequently Asked Questions
How much does a kitchen renovation cost in Australia in 2026?
Australian kitchen renovations in 2026 typically cost between $15,000 for a cosmetic refresh and $100,000-plus for a premium custom build. The most common mid-range project — full strip-out and rebuild with quality finishes, semi-custom cabinetry, and engineered stone or porcelain benchtops — sits between $30,000 and $60,000. Cabinetry is usually the single largest cost, accounting for 30 to 40 percent of the total budget. Plumbing relocation and any structural change to the layout are the next biggest cost levers.
How long does a kitchen renovation take in Australia?
A standard mid-range kitchen renovation in Australia takes six to ten weeks total, with three to five weeks of active on-site work where the kitchen is non-functional. The longest lead time is almost always cabinetry — typically 4 to 8 weeks for semi-custom and 8 to 14 weeks for fully custom. Order cabinetry the day the design is locked, not the day demolition begins. Premium renovations involving structural changes or imported materials can stretch to sixteen weeks or longer.
Do I need council approval for a kitchen renovation in Australia?
Most cosmetic kitchen renovations in Australia do not require council approval if you keep the existing layout and the existing footprint. You will need approval if you remove a load-bearing wall, change the building footprint, or make significant structural modifications. Plumbing relocation may require a plumbing permit depending on your state and council, typically taking one to three weeks for approval. Always check with your local council before signing the contract.
What should be in an Australian kitchen renovation contract?
An Australian residential kitchen renovation contract should include the parties' names and licence details, the scope of works matching your written scope document line by line, the contract price, payment terms tied to completed milestones rather than calendar dates, the variation process in writing, the defects liability period, deposit terms compliant with state regulations, insurance details, and a dispute resolution mechanism. Each Australian state's consumer building authority publishes specific guidance on what the contract must contain — read it before you sign.
What is the correct order of trades in a kitchen renovation?
The correct fit-out sequence is: cabinetry installation, benchtop template, benchtop fabrication and installation, plumbing connections, splashback installation, electrical fit-off, painting, appliance installation, and final clean. The benchtop must be templated after cabinets are installed, never before, because the template measures off the installed cabinetry. The splashback must be installed after the benchtop, never before, because it sits on top of the benchtop. Getting the sequence wrong creates rework, idle trade days, and cost.
Is engineered stone still legal in Australia for kitchen benchtops?
Engineered stone with crystalline silica content above 1 percent has been banned in Australia since 1 July 2024 under Safe Work Australia regulations introduced to prevent silicosis. Low-silica engineered stone (under 1 percent crystalline silica) remains legal, and most stonemasons have moved to porcelain slab and sintered stone alternatives that look identical to the old engineered stone products. If you are choosing a stone benchtop in 2026, confirm with your supplier in writing what the crystalline silica content is before signing the order — the compliance obligation is on you to verify.